The Network 21 Project will install a new campus network which will
provide a high capacity communications infrastructure to 200 buildings.
This project will create a data network with approximately 10,000 active
ports.
The Network 21 Project will be implemented in several stages:
-
Renovation or construction of wire closets to accommodate modern electronic
devices.
-
Installation of fiber optic cable between buildings and to wire closets
within buildings.
-
Installation, where necessary, of new wire from the wire closet to
the wall jack.
-
Installation and testing of electronics hardware and devices in the
communications closets.
-
Cutover from the legacy systems to the upgraded network.