Overview of the Cutover Process



Introduction


This document outlines the tasks and timing involved to migrate a department from the UCDNet or Network 21 Interim solution to the Network 21 ATM infrastructure. This involves removal of existing network hardware (including Department installed equipment) in Network 21 wiring closets, and installation and migration to the Network 21 ATM network.

As part of the Stage 3 cutover process, I.T. will provide monthly Network 21 Information Sessions. Network 21 Consultants will answer questions about cutover issues, notification, and cutover schedules. At cutover time, Cutover Implementation Teams are responsible for cutover to the Network 21 infrastructure and verifying connectivity.


Cutover Process


General Information

Stage 3 Cutovers: Department cutovers will commence in early July 1998. In most cases, one department VLAN at a time will be cutover to the Stage 3 infrastructure. In some cases, a partial VLAN will be cutover at one time, with the remainder of the VLAN to be cutover on a separate scheduled date. All cutovers will be coordinated with the department technical point-of-contact (POC) in the following manner